Past Projects
On each of the below projects Westwind performed all planning and scheduling, supervision, dirt work, underground, roads, concrete curbs, sidewalks, clearing, landscape, survey, quality control, MOT design and implementation, directional boring (when needed), material hauling, debris disposal hauled out, OSHA compliance and supplied all machines and personnel to complete the work.
Wetlands Mitigation & Restoration
|
Name |
Work Performed |
Location |
|
U.S. Dept. of Interior - Hole in the Donut |
9 years of dry season ecological restoration - completing 3,200 acres. |
Everglades National Park, Dade County, Florida |
|
City of Palm Coast - Lehigh Canal Rehabilitation |
Relocation of canal, installation of Geogrid and rock on the bottom to control water flow and avoid turbidity. Mitigation of surrounding areas. |
Flagler County, Florida |
|
Panther Island Mitigation Bank |
Creation and enhancement of approximately 700 acres of wetlands. |
Collier County, Florida |
|
Roberts Road Stack Dust |
Mitigation of hazardous material generated from old cement plant |
Flagler County, Florida |
|
Broward County Parks & Recreation, The West Lake Project - Phase 2 |
Environmental enhancement of approximately 250 acres of vegetated highlands, wetlands and canals. |
Broward County, Florida |
|
St. Johns River Water Management District - Fort Drum Conservation Area |
Redesigned and removed levees to restore natural hydrologic regime to the area that had been ditched and diked for farm use. |
Indian River County, Florida |
|
Northern Palm Beach Improvement District |
Snailkite Restoration at Baywinds. |
Palm Beach County, Florida |
|
FDOT I-595 Mitigation |
Wetlands mitigation of approximately 28 acres. |
Broward County, Florida |
|
South Florida Water Management District - Supply Canal for ENR |
Portion of Everglades Nutrient Removal Project |
West Palm Beach, Florida |
|
St. Johns River Water Management District - C 4 Canal Palm Bay |
Reshape, redirect, clean and widening of C-4 Canal to restore flow, install control structures, reshape and mitigate levees on storage areas. |
Brevard County, Florida |
|
St. Johns River Water Management District - Wastewater Treat Facility |
Build containment area and settlement ponds. |
Brevard County, Florida |
|
St. Johns River Water Management District - HerndonSwamp Levee |
Delicate work of mitigation of ponds with lower depth to convert settlement ponds to run-off ponds. |
Brevard County, Florida |
|
St. Johns River Water Management District - Sunny Hill Restoration |
Mitigation, clean up and fix outflows on old celery and rice farm fields. Restored flow. |
Lake County, Florida |
|
St. Johns River Water Management District - Crane Creek Dredging |
Removal and disposal of dredged material. |
Brevard County, Florida |
|
South Broward Resource Recovery Plant |
Wetland restoration along river banks. |
Broward County, Florida |
Underground Utilities
Lift Stations, Sewer and Water
In addition to all the underground work performed at all of Westwind's total site development and road jobs, the Company has also performed these specific underground work projects:
Bayshore Road Water Main Line - Lee County, FL
Relocation of 48" Main line for the City of Titusville - Brevard County, FL
Palm Coast Raw Water Main Line - Flagler County, FL
Beach Village Lift Station - Flagler County, FL
I-95 Utility Relocation - St. Johns County, FL
Waste Water Treatment Facility Pipe Relocation - Brevard County, FL
Relocation of Lehigh Canal - Flagler County, FL
St. Johns River Water Management District Sebastian Levee Containment Area 180-acre property, rectangular containment area with 18-foot high wall designed with the capacityto store more than 2 million cubic yards of muck from the Sebastian River - Brevard County, FL.
Relocation of Royal Palm Canal - Flagler County, FL
US-17 FDOT Pond, Approx 1,000,000 CY dug and hauled - Clay County, FL
Cigar Lake, Approx 1,000,000 CY dug and hauled - Flagler County, FL
Corkscrew Road Excavation, Approx 1,500,000 CY dug and hauled - Lee County, FL
Pond 65-1 at PC Town Center, Approx 900,000 CY dug and hauled, 63' deep, 22' below sea level - Flagler County, FL
West Palm Beach Airport Canal - Palm Beach County, FL
Pond 70-1 at PC Town Center, Approx 250,000 CY dug and hauled - Flagler County, FL
Panther Island Excavation, Approx 1,200,000 CY dug and hauled - Collier County, FL
Pond 60-1 at PC Town Center, Approx 300,000 CY dug and hauled - Flagler County, FL
Country Road 208, Quad Culvert Cast in Place - St. Johns County
Royal Palms Canal 48' Conspan Bridge with Key stone retaining walls - Flagler County
FDOT SR207 2 miles west of I-95 double barrel cast in place box culvert - St. Johns County
PC Town Center Pre-cast triple barrel Box Culvert - Flagler County
PC Town Center 130' of cast in place gravity wall - Flagler County
FDOT SR207 quad cover cast in place box culvert - St. Johns County
CR13 & SR207 intersection double barrel cast in place box culvert - St. Johns County
FDOT SR207 1/2 miles west of CR13 double barrel cast in place box culvert - St. Johns County
FDOT SR514 single barrel cast in place box culvert - Brevard County
FDOT SR520 830' of cast in place gravity wall - Brevard County
FDOT SR78 quad culvert cast in place box culvert - Lee County
FDOT SR78 triple barrel cast in place box culvert - Lee County
FDOT SR78 (2) double barrel cast in place box culvert - Lee County
FDOT SR520 (3) single barrel cast in place box culvert - Orange County
FDOT SR520 (2) double barrel cast in place box culvert - Orange County
FDOT SR520 triple barrel cast in place box culvert - Orange County
Ranger Drainage District double barrel cast in place box culvert - Orange County
|
FDOT |
SR 520 Brevard II |
Brevard County |
$12.7 Million / 24 months |
|
FDOT |
SR 520 Brevard County |
Brevard County |
$8.8 Million / 24 months |
|
FDOT |
Construct Park and Ride Project |
Broward County |
$1.6 Million / 12 months |
|
FDOT |
Add Lanes and Reconstruct Flamingo Road |
Broward County |
$4.0 Million / 12 months |
|
FDOT |
Alligator Alley Boat Ramps |
Broward County |
$4.4 Million / 12 months |
|
FDOT |
US - 17 |
Clay County |
$3.3 Million / 12 Months |
|
FDOT |
Surcharge Embankment for SR 951 |
Collier County |
$23.5 Million / 36 months |
|
FDOT |
SR 78 Bayshore Road East |
Lee County |
$14 Million / 24 months |
|
FDOT |
SR 78 Pine Island Road |
Lee County |
$6.5 Million / 24 months |
|
FDOT |
Veterans Parkway |
Lee County |
$9.6 Million / 12 months |
|
FDOT |
SR 520 Orange County |
Orange County |
$20.4 Million / 36 months |
|
FDOT |
Add Lanes and Reconstruct US 27 |
Palm Beach County |
$7.5 Million / 18 months |
|
FDOT |
SR 207 West Side |
St. Johns County |
$12.6 Million / 24 months |
Mining
Operation, Development and Permitting
|
Name |
Work Performed |
Location |
|
Cherokee Crush Stone Mine |
Planning, permitting, setup, excavating, crushing, screening, FDOT classification, sales and MSHA safety training and compliance |
Broward County, FL |
|
Westwind Corkscrew Mine |
Planning, permitting, setup, excavating, dredging, crushing, screening, FDOT classification, sales, MSHA safety training and compliance |
Lee County |
|
Hastings Shell Rock Mine |
Planning, permitting, setup, excavating, FDOT classification, sales, MSHA safety training and compliance |
St. Johns County, FL |
|
Bahamas Rock Quarry |
Excavation of lime rock for the owner with large draglines |
Freeport, Grand Bahamas |
|
Sawgrass Mine |
Planning, permitting, setup, excavating, crushing, screening, FDOT classification, MSHA safety training and compliance |
Dade County, FL |
|
Meekins Mine |
Planning, permitting, setup, excavation with cutter head dredge, FDOT classification, sales, MSHA safety training and compliance |